1.1Senator Dibble moved to amend
H.F. No. 3035, as amended by the Senate March
1.29, 2022, as follows:
1.3(The text of the amended House File is identical to
S.F. No. 2676.)
1.4Page 3, line 21, before "
Annually" insert "
(a)"
1.5Page 3, after line 28, insert:
1.6"
(b) The Metropolitan Council must notify the chairs and ranking minority members of
1.7the legislative committees with jurisdiction over transportation policy and finance
within
1.8seven calendar days of making a determination that:
1.9(1) the anticipated Southwest light rail project completion date is delayed by six
months
1.10or more beyond the estimated completion date determined as of the effective date of
this
1.11section;
1.12(2) the anticipated Southwest light rail project completion date is delayed by six
months
1.13or more beyond the most recent estimated completion date;
1.14(3) the total Southwest light rail project cost is anticipated to increase by five
percent
1.15or more above the project cost estimate determined as of the effective date of this
section;
1.16or
1.17(4) the total Southwest light rail project cost is anticipated to increase by five
percent
1.18or more above the most recent cost estimate."